Class 110: Baseline Schedules
WHAT IS A BASELINE SCHEDULE?
A baseline schedule
is a fixed project schedule that is the standard by which project performance
is measured.1 It captures how the project team plans to execute a
project in alignment with contractual requirements. Baseline schedules forecast a project’s
duration prior to incorporating any real time issues like late material deliveries,
inclement weather, slow/poor workmanship, etc. The real-time issues are captured in updated schedules which can
be compared to the baseline schedule to reveal variances. However, most
baseline schedules reflect contractual contingency time in activity durations
to account for common project delays.
Example of a Baseline Schedule:
The example above shows a
typical construction schedule for a high-end mixed-use skyscraper. The baseline schedule captures the planning
and sequencing that must take place before construction begins. Construction projects are complex, so creating
a baseline schedule to outline the original plan for the project is an
important step. As the project
progresses and changes are made to the schedule, the schedule is updated and
can be compared to the baseline schedule. Baseline schedules are often represented in the gantt chart as a
thin yellow line underneath the updated schedule’s activities or a yellow
diamond underneath a milestone, as in the example above. A baseline schedule compared to an updated
schedule provides a quick view of variances to activity start and finish dates.
Why are Baseline Schedules Important?
Baseline schedules typically
incorporate the established contractual schedule requirements. This allows the project team to develop an
efficient sequence of work for all subcontractors to follow.
Baseline schedules can be
included in forensic reviews of a project when trying to determine the impact
project events have on completion milestones. Often a baseline schedule comparison
in a forensic delay analysis can identify events that trigger delay or work
that has been re-sequenced.
When using certain
software, a baseline schedule compared to an updated schedule helps analysts
identify activities that were added to the schedule after the latest baseline was
created, which can indicate a possible change order or delay event.
Baseline Schedule
Summary:
1. Critical contractual dates are typically incorporated in the baseline schedule.
2. Baseline schedules can help identify schedule delays as the project progresses and schedule updates are performed.
Key Terms:
Update Schedule – a dynamic version of the baseline schedule that reflects the most current information on the project
Gantt Chart – a type of bar chart that provides a graphical representation of a schedule that includes the activities that make up a project
Resources:
0 comments: